URETEK
call

DCP-Guided Deep Injection to Stabilize Weak Subsoils and Lift Settled Slabs at a Landfill Weigh Station

Project at a Glance

Location

Upstate New York

Structure Type

Four concrete approach and departure slabs (about 18 inches thick) at an active, county-operated landfill weigh station

Core Challenge

Settlement had dropped the weigh-station slabs enough to create unsafe transitions, over weak soils about four feet down, and the station had to keep weighing loaded trucks throughout the repair

Verification

Dynamic Cone Penetrometer (DCP) testing through each slab to locate the weak soils and set depths, continuous slab-movement monitoring during lifting, and a preload check under a loaded semi-truck before closeout

URETEK Scope

URETEK Deep Injection (UDI): 5/8-inch sacrificial steel tubes driven to about four feet, staged injection of structural polymer to stabilize the subsoils and lift the slabs, adjusted slab by slab

Result

Weak subsoils stabilized under all four slabs and the entrance slabs raised about 1.6 and 2.5 inches with joints returned to level; exit slabs stabilized and lifted within safe limits, in two days without closing the station

cover image

An operating landfill weigh station in New York: URETEK stabilized the weak subsoils and lifted the settled approach and departure slabs while the station kept weighing trucks

The Problem: Settled Weigh-Station Slabs Over Weak, Unknown Soils

At an active, county-operated landfill in New York, the concrete slabs serving the entrance and exit lanes of the weigh station had settled. Four slabs were affected, the entrance approach and departure and the exit approach and departure, and the differential movement had created uneven, unsafe transitions for the loaded trucks crossing the scale every day.

The cause was below the concrete, and it was unknown. The roughly 18-inch-thick slabs were dropping because the soils supporting them had weakened, but no one had characterized those soils. Simply pumping material into the voids directly under the slabs might raise them briefly without addressing what was actually causing the settlement.

The repair also had to happen around a working facility. The weigh station had to keep weighing loaded trucks, so the work was staged lane by lane, and each slab had to carry heavy vehicle traffic again as soon as its area was treated.

cover image

Structural polymer injected through 5/8-inch sacrificial steel tubes: staged injection stabilized the weak soil at depth, then raised the slabs under continuous movement monitoring

Why Slab Replacement or Simple Void-Filling Was Not the Answer

Tearing out and repouring four 18-inch slabs would have shut the weigh station down. Demolition, forming, pouring, and curing take a lane out of service for days or weeks, and on a facility that has to weigh every load, that downtime is the whole problem. Replacement also does nothing about the weak soils below, so new slabs could settle the same way.

Conventional slab-jacking that only fills the voids directly beneath the concrete has the opposite gap: it can raise a slab, but it does not strengthen the weak soil a few feet down that let the slab settle in the first place. Without treating that layer, the fix is temporary.

What the site needed was a method that could first find and stabilize the weak soils at depth and then lift the slabs, all through small holes, with the station staying open. That is what URETEK Deep Injection delivers.

The URETEK Solution: Test First, Stabilize the Soil, Then Lift

Because the subsurface was unknown, the work started with measurement. Crews drilled through the roughly 18-inch slabs and ran Dynamic Cone Penetrometer (DCP) testing beneath each of the four slabs. The tests found weak soil under every one, at a depth of about four feet, and the profiles were not identical from slab to slab, so the treatment was tuned to each location rather than applied uniformly.

Staged Injection: Stabilize, Then Raise

Crews drilled 5/8-inch access holes and drove 5/8-inch sacrificial steel injection tubes to about four feet, the depth the DCP testing identified. A two-component, high-density expanding structural polymer was then injected in stages. At the deeper points, the expanding polymer compacted and densified the weak soil surrounding the tubes; injections nearer the surface then filled voids beneath the slabs and applied controlled upward pressure to raise the concrete. Slab movement was watched throughout, so material delivery could be stopped or redirected as each slab responded.

The slabs did not all behave the same way. The two entrance slabs responded immediately and came back to level. On the exit side, the slabs were interlocked in a way the drawings did not show, and excess concrete at a curb and an adjacent retaining wall restricted how far the exit departure slab could move. Rather than force them and risk cracking the concrete, the crew lifted the exit slabs only as far as the existing construction would safely allow.

Proven Under the Loads It Carries

Verification happened under real traffic. Several locations treated on the first day needed more injection on the second: when a loaded semi-truck crossed the entrance slabs and showed slight deflection, crews returned for targeted spot injection. The slabs were then preloaded and re-checked under heavy vehicle traffic before the injection ports were sealed and the site was closed out. The project’s closing engineering memo concluded that the treated subsoils were stable and that the slabs had been lifted as far as possible without damaging the existing concrete.

cover image

Drilling through the roughly 18-inch-thick slab to place an injection tube: access holes were drilled and tubes driven to the depth the DCP testing identified, about four feet

What the Numbers Showed

The figures behind this repair came from the DCP logs, the daily field reports, and the elevation checks: the record of what was tested, injected, and lifted.

The slabs were about 18 inches of concrete, and DCP testing found weak soil roughly four feet down beneath all four. Crews placed 5/8-inch sacrificial steel tubes at that depth and injected a two- component expanding structural polymer, 3,369 pounds in total across the four slabs over two working days.

The lift was measured slab by slab: the entrance approach slab came up about 1.6 inches and the entrance departure slab about 2.5 inches, with the entrance joints returned to level. On the exit side, where interlocked concrete and an adjacent retaining wall limited safe movement, the exit approach slab was raised about 3/8 inch and the exit departure slab about 1/2 inch.

Control mattered as much as quantity. Slab movement was monitored continuously during injection, first-day areas that deflected under a loaded truck were re-injected the next day, and the slabs were preloaded and re-checked under heavy vehicles before closeout, so the result was confirmed under the loads the slabs actually carry.

Results

The program stabilized the failing support and restored the slabs safely, without taking the weigh station out of service.

Key Takeaways for Similar Projects

Test before you lift. The soils were unknown, so the work began with DCP testing through each slab. It found a weak layer about four feet down, and different profiles under different slabs, which is what let the crew treat the cause and tune the work location by location.

Stabilize the soil, not just the voids. Filling the voids under a slab can raise it, but only stabilizing the weak soil at depth addresses why it settled. Staged injection did both: densify the deep soil first, then lift.

Let field conditions govern the lift. When the exit slabs turned out to be interlocked and restrained by adjacent concrete, the crew lifted them only as far as was safe rather than forcing them. Knowing when to stop protected the existing structure.

Verify under the real load. Checking the slabs under a loaded truck, re-injecting where they deflected, and preloading before closeout confirmed the repair against the traffic it has to carry, not just its appearance at rest.

Do You Have Settling Slabs Over Weak Soil at a Facility That Cannot Shut Down?

If settlement is opening unsafe transitions in slabs or pavement you cannot afford to close, especially where the weakness is in the soil below, URETEK can help. We test the subsurface, stabilize the weak soils, and lift the concrete back toward grade through small holes, with the facility in service. We will investigate your subgrade with in-situ testing, design a staged injection program, and verify the lift under real loads, so your team gets a stabilized, safer surface without demolition and with minimal downtime.

Contact URETEK today

URETEK

We Get to the Bottom of It. Engineering-led, trenchless ground improvement since 1989, with more than 10,000 projects worldwide. Questions about the soil beneath your infrastructure? Reach out today.

Request an Assessment

Phone
Address

13900 Humble Road, Tomball, TX 77375


Privacy PolicyTerms of ServiceSitemap
linkedin iconfacebook icon

© 2026 URETEK USA, Inc. All rights reserved.